1. Discovery and analysis
We review the process, cycle times and bottlenecks together on site. The goal is to define where and how automation fits and how success will be measured. The output of this step is a pre-feasibility study and an application proposal.
- What you prepare: part dimensions and weights, product mix, target cycle time, shift pattern.
- Layout drawing, details of existing machines and conveyors, short videos of the process.
- A project owner on your side and access to the site.
2. Concept and simulation
Cell layout, robot model, gripper concept and safety approach are defined. Reach and cycle time are verified in 3D simulation, so the investment decision rests on a demonstrated result rather than an assumption. Scope and quote are finalised at the end of this step.
- What you prepare: 3D models or samples of the parts, pallet and carton dimensions.
- Line communication needs (PLC, MES, ERP) and any internal technical standards.
- Participation of the decision makers who will approve the concept.
3. Design and build
Gripper, fixtures, mechanical structure, control cabinet, safety and software are developed by one team. The risk assessment is detailed at this stage and safety functions are built into the design.
- What you prepare: timely feedback on design approvals.
- Enough real parts or packaging material for FAT.
- Planning of site utilities such as power, compressed air and network.
4. Factory acceptance test (FAT)
Before shipping, the cell is tested in our workshop with your real parts. Cycle time, product changeover, fault scenarios and safety functions are checked together. Open items are listed and closed before shipment.
- What you prepare: production and maintenance representatives to attend FAT.
- Acceptance criteria agreed in writing in advance.
5. Installation and site acceptance test (SAT)
The cell is installed on site, connected to the line and commissioned. During the site acceptance test it runs under real production conditions. Your operators and maintenance staff are trained, and technical documentation and conformity documents are handed over.
- What you prepare: a cleared installation area and ready utilities.
- A planned production stop or changeover plan.
- Operators and maintenance staff for training.
6. Service
We stay with you after commissioning. Remote support, preventive maintenance, spare parts and program updates for new products keep the cell running. When you want to add a new product or station, the process restarts with a shortened discovery step.